Masthead Image

LRT Phase 1 Tunnel

Location: University Station, Edmonton

Client: PCL

Value: $2,000,000

Duration: 24 months

This excavation project was the initial phase of a multi-phase expansion of Edmonton's South LRT line. For this project we excavated and backfilled launch shaft and an 84-foot deep recovery shaft, prepared trackway, removed and capped storm and sanitary sewers, gas lines and irrigation lines, and hauled out 18,000 cubic meters of tunnel tailing without slowing progress.

From small projects to larger subdivision work, excavation was where we started and it's still the backbone of our business.